NRT_Sydney Metro Northwest Construction 2017-2018
We participated in Sydney Metro Tunnel Construction Project and completed one of the stage from Bella Vista to Epping station within time frames.
Additionally, Boilermakers & Coded welders had completed spindle repair work as requested by Client.
All 50+ qualified tradesmen had completed RISI induction & medical test for Railway Project.
Location | Bella Vista, Epping, Cherrybrook, Showground, Castle Hill |
Job Title | Sydney Metro Northwest Construction |
Duration | 8 months from Aug 2017 – April 2018 |
Service | Tunnelling – Installation of the railway tracks, track slab and etc |
Scope of Work | Tunnelling work from Bella Vista to Epping as part of Stage 1 of Sydney Metro |
Project Resourcing
|
50+ personnel, especially Trades Assistant and Coded Welders & Boilermakers included for spindle repair work. |