GE_ALSTOM Breakdown, Mt Piper Power Station
Mt piper breakdown
On march 17th our team attended a tube leak in mt piper unit 2 boiler where we completed the repair of 26 tubes
well within the allocated schedule allowing Energy Australia to get back to production with out further delays.
Field & Class of Trades: Special-Class Welders and Advanced Riggers
Tradesmen Deployment: Australia-Wide
Work Hours: 24hrs (12hr shifts , 8 days)
Area of works: Super Heater ( B3 , Inconel tubes )
Total Crew Deployed: 9 Specialised, Qualified and Experienced Tradesmen
Total Lost Time: Nil