GE FIELDCORE_Installation of GT ECON BYPASS LINE

 

 Client GE FIELDCORE INTERNATIONAL
Location SWANBANK POWERSTATION
Job Title Installation of GT ECON BYPASS LINE
Service Identify the inlet line & remove the insulation

Installation the 2-equal tee after a taking-off point

Install the MOV in the GT Econ Bypass Line (Welding – SA105 GR.B)

Paint the existing supports (Spec. HI TEMP 400)

 

Scope of Work(OCT 2019)

  • Installation and Welding (On material SA105 GR.B)

Project Resourcing

Onsite personnel included Coded Welders & Rigger & Boilermaker & Trades Assistant

Project Achievements

We’ve proudly completed the project with high standard performance as per the client’s request

  • Zero (0) Lost Time Incident during the project
  • Zero failure rate on all welding
  • Project delivered on time
  • Protech Welding Pty Ltd worked closely with the client nominated project & quality engineer (consultant)