GE_ALSTOM Scheduled Shutdown, Mt Piper Power Station

SEP 2016 – OCT 2016.

Protech Welding  was given the opportunity to co-participate on the Mt Piper scheduled shutdown.

Initial crew of half a dozen carried out the ‘scope of works’.

Within the first week, Protech Welding  was requested to supply an additional team of 21 specialised tradesmen within 24 hours of notice.

Within the 2nd week, Protech Welding  was again requested to supply an additional team of 16 specialsed tradesmen within 18 hours of notice.

Supply, Operate, Manage and Documentation support was also provided as a complimentary service to ensure the Shutdown progressed on time and within budget.

 

KakaoTalk_20161013_162726150          KakaoTalk_20170207_121419471           8

KakaoTalk_20161013_162551195          KakaoTalk_20161013_162708173

 

 

Field & Class of Trades:           Special-Class Welders, 1st Class Boilermakers, and Advanced Riggers

Tradesmen Deployment:       Australia-Wide

Work Hours:                              24hrs (12hr shifts , 6 weeks)

Area of works:                          Air Heater, Panel Tubes (347H Stainless Steel), Plates, Economiser,Swing Stages in the Boiler
                                                      where after GE ALSTOM / ENERGY AUSTRALIA’s survey was conducted.

Total Crew Deployed:             43 Specialised, Qualified and Experienced Tradesmen

Total Lost Time:                       Nil