GE POWER CONVERSION_Wind Tower Rotor Repair
Client | GE POWER CONVERSION |
Location | COOPERS GAP WINDFARM) |
Job Title | Neutral Connection Repair |
Service | Cu-ETP Neutral Connections welding training by GE France at Nancy, France during 24th Jun ~ 27th Jul
Global Wind Organisation (GWO) Training at Mulgrave, Melbourne During 10th Jul ~ 18th Jul Remove the insulation by GE & PW Repair by welding with filler material Insulate the repaired connection by GE & PW |
Scope of Work
- Rotor Repair Welding (On material CuNi)
Project Resourcing
Onsite personnel included Coded Welders
Project Achievements
We’ve proudly completed the project with high standard performance as per the client’s request
- Zero (0) Lost Time Incident during the project
- Zero failure rate on all welding
- Project delivered on time
- Protech Welding Pty Ltd worked closely with the client nominated project & quality engineer (consultant)