VISY (Coolaroo) Scheduled Shutown
20th of Dec. – 27th of Dec. 2015
When it was time for the next phase of shutdown works for VISY’s Coolaroo CEP (VIC), Protech Welding P/L was the first contact on the list to manage, operate and deliver the shutdown project! Protech Welding assigned 22 Special-Class tradesmen working in a 24 hour (12 hr shifts) rostering cycle to replace a 1 inch stainless steel single tube on a Super-Heater as well as other patch works and refinements.
Again, Protech Welding P/L outperformed VISY’s expectation and as a result have secured the appointment to carry-out the next scheduled shutdown project due in March, 2016.