60 CASTLEREAGH ST_FLAGPOLE WALL REINFORCEMENT

60 Castlereagh St – Flagpole Wall Reinforcement DEC 2021

Location 60 Castlereagh St Sydney NSW 2000

Job Title Flagpole Wall Reinforcement Project

Service Welding/ Equipment and tool supply

Scope of Work

Work DescriptionWeight ValueTotal ProgressPlanActualVariance
Protection setup with Leather35%100%1001000
16 x New Plates Drilling20%100%1001000
16 x New Plates Welding15%100%1001000
Drilling on Aluminium pole5%100%851002
Replacing Thread bar / nuts10%100%851003
Painting / Chemset injection / QC docs supply15%100%01003
Total100%100%78.3%100%21.7%

Project Resourcing

Workshop personnel included Coded Welders and Boilermakers. The support team included Project Management, Quality Management, Project Engineer and Project Supervisor.

Documents Supplied

  • WPS & WPQR
  • Crew Qualification
  • WMS (Work Method Statement)
  • ITP
  • SWMS
  • Completion Report

Safety Plan for Work

(Health, Safety and Environment Performance (Inc. Subcontractors))

No.DescriptionCumulative
1SAFETY INTERACTIONN/A
2SCAFFOLDINGN/A
3TEST AND TAG, RIGGING INSPECTIONN/A
4WORKING AT HEIGHT (HARNESS)WAH Check
5DROP ZONE COVERED BY 3 X 3 LEATHER WELDING BLANKETN/A

Project Achievements

We’ve proudly completed the project with high standard performance on schedule.

All procedures were qualified and approved by International and Australian standards prior to the project commencement:

  • Zero (0) Lost Time Incident, Zero NCR during the project
  • Zero failure rate on overall welding
  • Project delivered on time and under budget
  • Protech Welding Pty Ltd worked closely with the client nominated Welding engineer/ consultant in headquarter to ensure all project quality requirements were exceeded for the duration of the project

Activities

  • Extensive interaction with our client to ensure quality of finished product was in line with practical requirements, especially to set up the repair methodology/ safety blanket at beginning stage.
  • Project and quality management