60 CASTLEREAGH ST_FLAGPOLE WALL REINFORCEMENT
60 Castlereagh St – Flagpole Wall Reinforcement DEC 2021
Location 60 Castlereagh St Sydney NSW 2000
Job Title Flagpole Wall Reinforcement Project
Service Welding/ Equipment and tool supply
Scope of Work
Work Description | Weight Value | Total Progress | Plan | Actual | Variance |
Protection setup with Leather | 35% | 100% | 100 | 100 | 0 |
16 x New Plates Drilling | 20% | 100% | 100 | 100 | 0 |
16 x New Plates Welding | 15% | 100% | 100 | 100 | 0 |
Drilling on Aluminium pole | 5% | 100% | 85 | 100 | 2 |
Replacing Thread bar / nuts | 10% | 100% | 85 | 100 | 3 |
Painting / Chemset injection / QC docs supply | 15% | 100% | 0 | 100 | 3 |
Total | 100% | 100% | 78.3% | 100% | 21.7% |
Project Resourcing
Workshop personnel included Coded Welders and Boilermakers. The support team included Project Management, Quality Management, Project Engineer and Project Supervisor.
Documents Supplied
- WPS & WPQR
- Crew Qualification
- WMS (Work Method Statement)
- ITP
- SWMS
- Completion Report
Safety Plan for Work
(Health, Safety and Environment Performance (Inc. Subcontractors))
No. | Description | Cumulative |
1 | SAFETY INTERACTION | N/A |
2 | SCAFFOLDING | N/A |
3 | TEST AND TAG, RIGGING INSPECTION | N/A |
4 | WORKING AT HEIGHT (HARNESS) | WAH Check |
5 | DROP ZONE COVERED BY 3 X 3 LEATHER WELDING BLANKET | N/A |
Project Achievements
We’ve proudly completed the project with high standard performance on schedule.
All procedures were qualified and approved by International and Australian standards prior to the project commencement:
- Zero (0) Lost Time Incident, Zero NCR during the project
- Zero failure rate on overall welding
- Project delivered on time and under budget
- Protech Welding Pty Ltd worked closely with the client nominated Welding engineer/ consultant in headquarter to ensure all project quality requirements were exceeded for the duration of the project
Activities
- Extensive interaction with our client to ensure quality of finished product was in line with practical requirements, especially to set up the repair methodology/ safety blanket at beginning stage.
- Project and quality management