GE_ALSTOM Breakdown, Mt Piper Power Station
On April , 2017
Our team was called to mobilize for a Tube leak at Mt piper by Ge Energy and within 4 hours our team was on the deck ready for Wash down and to commence repairs on completion of surveys.
Our team was able to once again complete repairs on wall tubes and internal tubes to the boiler well within the scheduled handover time.
Field & Class of Trades: Special-Class Welders , Pipe Fitters and Advanced Riggers
Tradesmen Deployment: Australia-Wide
Work Hours: 24hrs (12hr shifts , 5 days)
Area of works: Economizer
Total Crew Deployed: 10 Specialised, Qualified and Experienced Tradesmen
Total Lost Time: Nil