GE_ALSTOM Breakdown, Mt Piper Power Station

On April , 2017

Our team was called to mobilize for a Tube leak at Mt piper by Ge Energy and within 4 hours our team was on the deck ready for Wash down and to commence repairs on completion of surveys.
Our team was able to once again complete repairs on wall tubes and internal tubes to the boiler well within the scheduled handover time.

 

KakaoTalk_20170418_135628324 KakaoTalk_20170418_135620466

KakaoTalk_20170418_135625609 KakaoTalk_20170418_135615282

 

Field & Class of Trades:           Special-Class Welders , Pipe Fitters and Advanced Riggers

Tradesmen Deployment:       Australia-Wide

Work Hours:                              24hrs (12hr shifts , 5 days)

Area of works:                          Economizer

Total Crew Deployed:              10 Specialised, Qualified and Experienced Tradesmen

Total Lost Time:                       Nil