Veolia project

We were called in to Orora botany project to install various stainless steel piping to their new silo’s and pipe racks.

We completed the scope within time frames provided by our client to provide all clients with the desired outcome.

 

 

KakaoTalk_20171010_110245709

KakaoTalk_20171010_110247595KakaoTalk_20171010_110251706

 

 

 

 

 

 

 

KakaoTalk_20171010_110253654

KakaoTalk_20171010_110255571

KakaoTalk_20171010_110257670

 

 

 

 

 

 

 

 

 

 

 

Field & Class of Trades:           Special-Class Welders, Pipe Fitters and Mechanical fitters

Tradesmen Deployment:       Australia-Wide

Work Hours:                              5,760 man hours

Area of works:                          Orora

Total Crew Deployed:              11 Specialised, Qualified and Experienced Tradesmen

Total Lost Time:                       Nil