We were called in to Orora botany project to install various stainless steel piping to their new silo’s and pipe racks.
We completed the scope within time frames provided by our client to provide all clients with the desired outcome.
Field & Class of Trades: Special-Class Welders, Pipe Fitters and Mechanical fitters
Tradesmen Deployment: Australia-Wide
Work Hours: 5,760 man hours
Area of works: Orora
Total Crew Deployed: 11 Specialised, Qualified and Experienced Tradesmen
Total Lost Time: Nil

On April , 2017
Our team was called to mobilize for a Tube leak at Mt piper by Ge Energy and within 4 hours our team was on the deck ready for Wash down and to commence repairs on completion of surveys.
Our team was able to once again complete repairs on wall tubes and internal tubes to the boiler well within the scheduled handover time.
Field & Class of Trades: Special-Class Welders , Pipe Fitters and Advanced Riggers
Tradesmen Deployment: Australia-Wide
Work Hours: 24hrs (12hr shifts , 5 days)
Area of works: Economizer
Total Crew Deployed: 10 Specialised, Qualified and Experienced Tradesmen
Total Lost Time: Nil

Mt piper breakdown
On march 17th our team attended a tube leak in mt piper unit 2 boiler where we completed the repair of 26 tubes
well within the allocated schedule allowing Energy Australia to get back to production with out further delays.
Field & Class of Trades: Special-Class Welders and Advanced Riggers
Tradesmen Deployment: Australia-Wide
Work Hours: 24hrs (12hr shifts , 8 days)
Area of works: Super Heater ( B3 , Inconel tubes )
Total Crew Deployed: 9 Specialised, Qualified and Experienced Tradesmen
Total Lost Time: Nil

Fabrication of one steel tank
Our team consisting of 2 boilermakers and 2 special class welders completed a tank for turnkey again achieving a quality and on time result for our client.
Field & Class of Trades: Special-Class Welders, 1st Class Boilermakers, and Advanced Riggers
Tradesmen Deployment: Australia-Wide
Work Hours: 12hrs (12hr shifts , 4 weeks)
Area of works: Work shop . (AS/NZS 3678 Gr 350 )
Total Crew Deployed: 4 Specialised, Qualified and Experienced Tradesmen
Total Lost Time: Nil